Two High Court rulings in November 2026 set the rules for the Procurement Act's 30-day challenge limit. Bouygues kept its claim over a £15.4bn framework alive because day 30 fell on a Saturday. Verity Healthcare lost a £928m homecare challenge because time ran from publication on Find a Tender, not from its alert email.
You miss a place on a £15.4bn construction framework by 0.13 of a mark and the assessment summary lands on a Friday in December. On our count, day 30 of your window to issue a claim is Saturday 3 January. Bouygues issued on Monday 5 January and the High Court said on 19 November 2026 that it was in time. A tender notice for a £928m homecare framework goes up on Find a Tender on a Wednesday, your alert email arrives on the Friday and you issue 30 days after the Sunday. Verity Healthcare did that and on 3 November 2026 the High Court threw the claim out without a trial. The two rulings came 16 days apart. What separates them is the day the 30 days started and how the last day was counted.
If you bid under the Procurement Act 2023, these judgments answer the questions your bid team asks the day a bad result comes in:
- When does my 30 days start: the day the notice or assessment summary is published, or the day someone in my company reads it?
- Does a weekend or a Christmas shutdown at the end of the period give me extra time?
- If the authority extends the standstill, does my deadline for a claim move with it?
- Does the time it takes to get legal advice count against me?
- Can I ask the court for more time, and when do I have to ask?
What happened in Bouygues v Secretary of State for Education?
The Department for Education’s CF25 Construction Framework 25 has ten lots, an estimated value of £15.4bn and a six-year term from 16 January 2026 with a two-year option (Bouygues (U.K.) Ltd v Secretary of State for Education [2026] EWHC 2998 (TCC), paragraph 6; framework notice 2025/S 000-080063). Bouygues bid for Lot 2 only. On Friday 5 December 2025 it received the assessment summary and the contract award notice: 11th with 74.67 marks against McLaren’s 74.8 in 10th (paragraphs 7 and 22).
The department extended the standstill to 5 January and refused the complaint on 30 December (paragraphs 8 to 11). The claim was filed at 16.18 on Monday 5 January 2026 (paragraphs 4 and 12).
Coppel J held that time ran from 5 December, that “the last day of the 30-day period stipulated by s. 106(2) was Saturday 3 January 2026” (paragraph 49) and that, because the Act has no rule for a period ending on a day the court office is closed (paragraph 50), the rule in Pritam Kaur v S Russell & Sons [1973] QB 336 applies: the period runs to the next day the office is open and “expired on 5 January 2026” (paragraphs 69 to 79). Do not plan on it: the judge noted that Bouygues could have filed on Friday 2 January (paragraph 92(ii)), and that the Christmas shutdown and the extended standstill “do not, in and of themselves, constitute a good reason” for more time (paragraph 95(iv)).
What happened in Verity Healthcare v Cambridgeshire?
Cambridgeshire, the county authority, is procuring a Homecare Framework worth an estimated £928,080,000 including VAT over up to ten years (Verity Healthcare Ltd v Cambridgeshire County Council [2026] EWHC 2830 (TCC), paragraphs 1 and 2). The questionnaire made a CQC rating of Good or Outstanding a gateway condition (paragraph 8), flagged in the planned procurement notice of 25 March 2026 (paragraph 78). The tender notice went up on Find a Tender on Wednesday 15 July 2026 at 2.28pm (paragraphs 14 and 15). Verity’s aggregator alert arrived at 4.41pm on Friday 17 July; Verity logged into the portal at 10.50pm on Saturday 18 July (paragraphs 15 and 44). It pleaded first awareness on 19 July and issued its claim on 17 August.
Jefford J found actual knowledge “at latest on 18 July” (paragraph 70), drew an adverse inference from evidence that “sought to obfuscate” the alert date (paragraph 73), and held that a reasonably well-informed and diligent supplier ought to have known of the condition “on the date of publication”, 15 July (paragraph 74). A grace period “of a day or two” would still have left the claim out of time (paragraph 83). Verity had not applied to extend time, so “this issue does not arise” (paragraphs 86 to 88), and the judge would have refused one (paragraphs 89 to 94). Summary judgment for the authority (paragraph 95).
How do the two cases compare?
| Bouygues v DfE (claim survived) | Verity v Cambridgeshire (claim dismissed) | |
|---|---|---|
| Contract | CF25 Construction Framework 25, est. £15.4bn | Homecare Framework, est. £928,080,000 inc VAT |
| Stage challenged | Framework award, Lot 2 (11th by 0.13 marks) | Gateway condition in the questionnaire (CQC Good or Outstanding) |
| Day the clock started | 5 December 2025, receipt of the assessment summary | 15 July 2026, publication of the tender notice |
| What the supplier said started it | 5 December (not disputed) | 19 July, when it said it first read the notice |
| Day 30, on our count | Saturday 3 January 2026 | Thursday 13 August 2026 |
| Claim issued | Monday 5 January 2026 | Monday 17 August 2026 |
| Extension asked for | Yes, in the alternative; would have been granted | No; judge said it would have been refused |
| Outcome | In time; claim continues | Out of time; summary judgment for the authority |
Source: the two judgments as cited above. “Day 30, on our count” counts the day the clock started as day 1 (5 December plus 29 days; 15 July plus 29 days). The Verity judgment does not state a day count.
When does the 30 days start?
Section 106(2) gives you 30 days “beginning with the day on which the supplier first knew, or ought to have known” of the circumstances. Both judges treated day 1 as the day the information reached you, not the day you understood it. For an assessment summary, “it will be an unusual case in which time does not start to run from the date of receipt of that summary” (Bouygues, paragraph 38); time to digest it and to take legal advice sits inside the 30 days (paragraphs 41 to 43). For a tender notice, setting alerts on Find a Tender or Google “is what suppliers should do and do do” (Verity, paragraph 75), a weekly alert cycle counts against the supplier (paragraph 76), and a supplier “cannot rely on its own inactivity” (paragraph 79).
The point your sales team can act on this week: a weekly aggregator alert can cost you two or three of your 30 days before anyone has read the notice. Verity lost three. A daily alert on Find a Tender costs nothing.
Does the standstill end or the Christmas shutdown move the deadline?
No. The end of the standstill “is not necessarily the same as the date of expiry of the limitation period” and “It was entirely a matter for the Claimant to ensure that proceedings were commenced within time” (Bouygues, paragraph 92(iv)). The standstill stops the contract being signed; the 30 days limits your right to sue. Extending the first does not extend the second, and Coppel J said authorities “should be able, in the great majority of cases, to predict with accuracy the date on which limitation expires” (paragraph 44).
The court can extend time for good reason, up to three months (section 106(3) and (4)), but only if you ask. Verity did not. Put the application in the claim form, in the alternative, as Bouygues did.
What should bidders do before the next assessment summary lands?
Our consultants see three gaps in supplier bid teams. Nobody owns the limitation date: the summary goes to the bid writer, the challenge letter goes to the lawyers a week later, and the 30 days is a fortnight gone. The date goes in the diary the day the summary arrives, counted as day 1. Alerts run weekly through an aggregator with nobody watching Find a Tender. And the evidence drifts: in Verity the supplier’s account of when it first saw the notice changed between its letter, its pleading and its witness statements (paragraph 73); your portal log-ins and your inbox are the record. Get the challenge letter out in the first week and decide on the claim with two working weeks in hand. Nexus does not give legal advice; our bid leadership work is about not needing it.
The dates you should know
| Date | What happened | Why it matters |
|---|---|---|
| Fri 5 Dec 2025 | DfE assessment summary and contract award notice received (Bouygues, para 7) | Day 1 of Bouygues’ 30 days |
| Sat 3 Jan 2026 | Day 30 (Bouygues, para 49) | Court office closed, so the period ran on |
| Mon 5 Jan 2026, 16.18 | Bouygues files its claim (Bouygues, para 12) | In time under the Kaur rule; judgment 19 Nov 2026 |
| 16 Jan 2026 | CF25 term starts, six years plus a two-year option (Bouygues, para 6) | Framework concluded; the remedy is likely to be damages |
| Wed 15 Jul 2026, 2.28pm | Cambridgeshire tender notice first accessible on Find a Tender (Verity, para 15) | Day 1 of Verity’s 30 days, as the court found |
| Fri 17 Jul 2026, 4.41pm | Verity’s aggregator alert email arrives (Verity, para 44) | Two days gone before anyone read the notice |
| Sat 18 Jul 2026, 10.50pm | Verity logs into the portal (Verity, para 15) | Actual knowledge at the latest, as the court found |
| Thu 13 Aug 2026 | Day 30 from 15 July, on our count | The claim had to be issued by now |
| Mon 17 Aug 2026 | Verity issues its claim | Out of time; summary judgment 3 Nov 2026 |
| April 2027 | Cambridgeshire Homecare Framework due to start (Verity, para 118) | One reason damages were held adequate |
Source: the paragraphs cited in each row; “on our count” rows are our own arithmetic, shown under the comparison table.
What contracting authorities should take from this
Both judgments favoured the authority, and both say why: the gateway condition had been flagged in the planned procurement notice four months before the tender notice (Verity, paragraph 78), and an authority can calculate the limitation date itself (Bouygues, paragraph 44). So publish exclusion conditions as early as the planned procurement notice, record when every notice and assessment summary went out, diarise day 30 for every unsuccessful bidder, and treat a claim filed on the first working day after a weekend or bank holiday as probably in time. Our Procurement Act 2023 Compliance Reviews check the notice trail and the assessment summaries for exactly these points.
Questions bidders are asking
Does the 30-day limit under the Procurement Act 2023 run from the day I read the notice?
No. In Verity Healthcare v Cambridgeshire (3 November 2026) the court held that a reasonably well-informed and diligent supplier ought to have known of a published gateway condition on the date the tender notice was published on Find a Tender, and that a late alert email or a weekly alert cycle counts against the supplier, not the authority.
What if day 30 falls on a Saturday, Sunday or bank holiday?
In Bouygues v Secretary of State for Education (19 November 2026) the court applied the Pritam Kaur rule: where the last day falls on a day the court office is closed, the period runs to the next day it is open. Bouygues' day 30 was Saturday 3 January 2026 and its claim filed on Monday 5 January was in time. The judge also said the claimant could have filed on the Friday, so treat the rule as a safety net, not a plan.
Does an extended standstill period extend my time to bring a claim?
No. The court in Bouygues said the end of the standstill is not necessarily the same as the expiry of the limitation period and that it was entirely for the claimant to issue in time. The standstill stops the contract being signed; the 30 days limits your right to sue; they run separately.
Does time spent getting legal advice delay the start of the 30 days?
No. Coppel J held that time to digest the assessment summary and to take advice falls within the 30 days, and that taking legal advice is not a reasonable enquiry that postpones knowledge.
Can I ask the court for more time?
Yes, under section 106(3) for good reason, to a maximum of three months. You must ask: in Verity the court would not consider an extension that had not been applied for, and said it would have refused one. Bouygues asked in the alternative and the judge said he would have granted it because the counting point was novel.
Sources: High Court (Technology and Construction Court), Bouygues (U.K.) Ltd v Secretary of State for Education [2026] EWHC 2998 (TCC), judgment of Coppel J, 19 November 2026; High Court (Technology and Construction Court), Verity Healthcare Ltd v Cambridgeshire County Council [2026] EWHC 2830 (TCC), judgment of Jefford J, 3 November 2026; Find a Tender, CF25 Construction Framework 25 contract award notices referencing framework notice 2025/S 000-080063, December 2025; Procurement Act 2023, sections 51, 102 and 106; Construction Enquirer, “Bouygues wins first round in £15bn DfE framework legal battle”, 20 November 2026; Solicitors Journal, reports on both judgments, November 2026; Irwin Mitchell, “30 days can disappear faster than you think”, 6 November 2026; Local Government Lawyer, report on Verity Healthcare v Cambridgeshire, 4 November 2026.